Building 074 - Mayo

A faulty sprinkler head in Room C-162 at Mayo triggered a water flow alarm. UMPD and MFD responded 

and found water flooding the first floor. DEHS, DEM and FM responded, as did Fairview Security and
Emergency Management. A majority of the rooms in this hallway that were flooded were medical 
records rooms that are Fairview property. SMP provided security due to the sensitive nature of the
documents in the rooms requiring clean-up. Mavo was brought in to provide remediation. DEHS
provided follow-up the next day to determine what additional remediation will be needed. 


Extraction of  water by Clean Response - difficulty finding sanitary sewer that was not plugged.

C-162 Mayo area with broken sprinkler head

Fire department used wood to wedge sprinker head- water shut off to Mayo for a few hours

Failure piece for sprinkler head.  Room  temp was normal in room. 
Medical Records water on floor

Temporary power - Post water removal 12/8/2013

Fans drying area 12/8/2013