Armory Bldg#011 - sprinkler head release 3/11/2015

Old sprinkler head released in entryway to Armory
02:28 3/11/2015 - MFD and UMPD on scene water flow alarm.

Incident is believe to be caused by a combination of a hot entryway heater and the age of the sprinkler head.  FM has now shut off the entryway heater.  A new sprinkler head has been installed.

Unit heater in north Armory entryway.
As of 09:00 FM has fans and dehumidifiers on scene.  Carpets have been extracted.  Objects are in the process of being removed from the floor.  DEHS has completed initial assessment and will return later this week to check on progress.  Walls are not made of sheetrock.  No wall removal needed. No asbestos containing materials were affected as noted in a review of the building survey by Andrew Madsen, FM.