| Partially pumped out lower level mechanical space - G. Williams |
![]() |
| Water damaged lower level of mechanical space - dried |
Van Anh Thai, DEHS responded to UMPD. She contacted Gary (612-291-1139) who was on site at the time to obtain more info. Apparently an incoming water line broke and discharged clean water into the Mechanical Room. It was estimated that there was about 3 inches of standing water. She told Gary to go ahead and pump the water out and discharge it into the sanitary sewer. She told him to use a drain/cleanout located inside the building as a discharge point.
![]() |
| New four inch water line NW corner of mechanical space |
![]() |
| Water line in lower level was at the midpoint of the filter on the tank in the left center of the room. |
![]() |
| A note below the red label to the right of the fire panel indicates the high water mark on the lower level |
FM asbestos arrived at around 08:30 on March 27, 2014. Suspected pipe insulation was sampled for asbestos. Results will be available later on March 27, 2014.
![]() |
| Damp filter inside SUP002 |